Saturday, February 27, 2010

Stucco Color and Interior Doors





The stucco color was applied yesterday. It only took one day and it looks pretty good. We were expecting the trim to be a little lighter, but it may lighten up after a few days as it cures. The rock won't be installed until it warms up a little more, but probably within the next month.
On the inside of the house, the materials for all the baseboards, trim, and shelving was delivered. Today, the interior doors and closet shelving was started.

Sunday, February 21, 2010

Flooring Layout


Yesterday we decided on the flooring layout. We will have carpet in the bedrooms, bedroom closets, hallway, and in the living room. Tile will be in the bathrooms, laundry room, and the entryway. The Kitchen, dining area, and just past the entryway going into the kitchen will be solid wood flooring. Natalie hasn't finalized the flooring decisions yet, but will this week.

Interior Wall Texture


Last week the wall texturing was done.

Stucco Base Coat


On 2-17 the stucco base coat was put on

Friday, February 5, 2010

Sheetrock



Yesterday the sheetrockers put up all of the sheetrock in one day. Next the walls will be mudded and then the texture will be applied. The picture is from the living room looking into the kitchen. The first video is the living room, then the kitchen, and then the view out the back. The second video is of the basement.

Tuesday, February 2, 2010

Insulation



The insulation was put in last week and yesterday the sheetrock was delivered. We can't wait to see the house with sheetrock up!