Door and Front Porch




The glass was put in our front door and earlier this week the front porch concrete was poured. The shingles were delivered and the roof should be put up in the next couple of weeks.

Thursday, January 14, 2010

Electrical and Heating





The electirical and heating was started this week.

Sunday, January 10, 2010

Dried In With Windows and Doors



Yesterday the house was dried in and the windows and doors were installed. On the inside the ladder blocks were installed and a few odds and ends were taken care of. The front door is missing its glass, but it should be put in soon.

Thursday, January 7, 2010

Trusses and Roof Sheeting


The Trusses and sheeting for the roof were finally finished this week.